CHIPPEWA COUNTY ROAD COMMISSION ROAD PROJECTS

Tentative projects for the summer 2016 construction season:

 

 

13 Mile Road - Bruce Township - Project started May 2015.  Project completed in June 2016.

Forrest Road from 10 Mile Road to 11 Mile Road - Dafter Township - Project started June 23, 2014, to be completed summer of 2015. Project completed in August 2016.

Lockhart Road - Dafter and Kinross Townships - Project started August 11, 2016

Lost Lake Road - Whitefish Township - New Gravel Surface. Project to be completed spring of 2016. Project completed January 2016.

Gogomain Road - Pickford Township - Asphalt resurfacing from M-129 in Pickford to Pennington Road along with drainage improvements at the Clegg Road intersection.  Project started June 2016. Project was completed September 2016.

Mainstreet Pickford - Sidewalks, and curb and gutter improvements to downtown mainstreet in Pickford. Project started June 2016. Project completed September 2016.

Townline Road - Pickford Township - Asphalt resurfacing from M-129 to Hancock Road.  Project started June 2016.

Project completed September 2016.

Pavement Markings - Shunk Road (5 Mile to 9 Mile), Piche Road (6 Mile to M-28), Thompson Road (Tilson Rd to Mackinac Trail), Gogmain Road (Pennington Rd to M-48), and Tilson Road (M-28 to H-40). Project completed June 2016.

Prarie Road - Rudyard Township -Sand lift and new gravel surface along with slope and drainage improvements. Project will start at the end of the pavement at the Pine River bridge going West for .45 miles.  Project started May 2016.

North Hulbert Road - Hulbert Township - Clearing, culvert and drainage improvements, sand subbase and new gravel surface beginning at the bridge and going North for 0.75 miles. Project started May 2016. Project completed September 2016

Libby Road / 20 Mile Road - Pickford Township - Clearing, culvert and drainage improvements, sand lift, new gravel surface, guardrail improvements and slope restoration beginning at Riverside Drive and going West for 4,508'.  Project started May 2016.

Little Bear Creek Crossing on Teets Road - Rudyard Township - Replacing existing culverts with a concrete box culvert.  Teets Road between H-40 and the Biscuit Road will be closed starting August 15, 2016 for approximately

3 weeks. - Project started August 2016. Project completed October 2016

W. 5 Mile Road - Soo Township - Changing large culvert. Project completed September 2016

W. 5 Mile Road - Soo Township - Pavement resurfacing.

Teets Road Crossing - Rudyard Township - Pavement resurfacing. Project completed November 2016

Scenic Drive - Bruce Township - Pavement resurfacing.

Kincheloe Streets - Kinross Township - Pavement resurfacing.

 

MDOT PROJECTS IN CHIPPEWA COUNTY

M-123 - Culvert replacement at 3 locations West of Paradise - Whitefish Township - Replacing old culverts at the intersections of W. Farm Truck Trail, Lost Lake Road and a crossing approximately 1 mile West of Lost Lake Road.  Traffic will be maintained but will be down to one lane. Project completed October 2016.

© 2019  by Chippewa County Road Commission.  Proudly created with Wix.com